2017 CIP - Contract B – Project Update 10/16/17

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

On WEDNESDAY, OCTOBER 18, the contractor is scheduled to pave the surface course of asphalt on CAMPBELL. Click on the link below for more information.

CAMPBELL - pavement surface resched

WEST VILLA DR:

The Contractor has rescheduled the work for placing and grading the stone base and paving the asphalt base pavement on WEST VILLA to start on Monday, October 16, with a tentative schedule as follows:

On MONDAY 10/16 the contractor is scheduled to rough grade the stone base.

On TUESDAY 10/17 the contractor is scheduled to fine grade the stone base.

On WEDNESDAY 10/18 the contractor is scheduled to pave the asphalt base pavement.

Click the link below for the notification letter.

WVILLA - base pavement resched

FIRST AVE:

The Contractor has scheduled the work for placing and grading the stone base and paving the asphalt base pavement on WEST VILLA to start on Tuesday, October 17. The contractor anticipates this phase of work will take approximately 3 days, with a tentative schedule as follows:

On TUESDAY 10/17 the contractor is scheduled to rough grade the stone base. Additional stone material will be delivered, placed and graded.

On WEDNESDAY 10/18 the contractor is scheduled to place and grade the stone base. Remaining driveway ramps will be removed during this phase. We recommend that you remove any vehicles you will need to use during this period.

On THURSDAY 10/19 the contractor is scheduled to pave the asphalt base pavement.

Click the link below for the notification letter.

FIRST - base pavement

BROWN ST:

It is anticipated the contractor will begin the concrete work on BROWN later this week. More information will be available soon.