2017 CIP - Contract B – Project Update 10/3/17

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue miscellaneous clean up on CAMPBELL.

The contractor will continue placing topsoil on CAMPBELL. The contractor will also begin placing sod this week.

WEST VILLA DR:

The contractor will continue concrete work on the east side of WEST VILLA.  Access to driveways will be closed for several days in order to construct the new curb, driveway aprons and sidewalks, and allow for concrete curing time.

FIRST AVE:

The contractor will continue concrete work on FIRST.

BROWN ST:

On TUESDAY, OCTOBER 3, the contractor will begin work on transferring water services to the new water main. The contractor anticipates transferring 2-3 services per day. It will take approximately 3 days to transfer all services. All work is weather dependent and unknown utility conflicts may cause delays. Click the link below for more information.

The contractor will continue storm sewer installation and repairs on BROWN.