2017 CIP - Contract B – Project Update 9/23/17

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue miscellaneous clean up on CAMPBELL.

The contractor will continue placing topsoil on CAMPBELL. Sod will be placed soon. 

WEST VILLA DR:

THE CONTRACTOR WILL BE WORKING SATURDAY, SEPTEMBER 23 ON WEST VILLA GRADING PARKWAYS AND CLEAN UP.

On TUESDAY, SEPTEMBER 26, the contractor will begin the concrete wok on the east side of WEST VILLA.  Access to driveways will be closed for a maximum of 14 days in order to construct the new curb, driveway aprons and sidewalks, and allow for concrete curing time. Click the link below for the resident notice.

FIRST AVE:

The contractor will continue the roadway work on FIRST.

BROWN ST:

The contractor will continue with water main installation on BROWN.

The contractor will begin storm sewer installation and repairs on BROWN.