2017 CIP - Contract B – Project Update 9/21/17

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue miscellaneous clean up on CAMPBELL.

The contractor will continue placing topsoil on CAMPBELL. Sod will be placed soon.

WEST VILLA DR:

The contractor will continue concrete work on the west side of WEST VILLA.

FIRST AVE:

On THURSDAY, SEPTEMBER 21, the contractor will begin the roadway work on FIRST. As part of this phase, all pavement, all curb, all driveway aprons, and sidewalks indicated in spray paint will be removed. After removing the pavement, curb and sidewalks, the contractor will excavate for the pavement base. Then a new stone base will be placed and graded. Click on the link below for the resident notice.

BROWN ST:

The contractor will continue with water main installation on BROWN.

On THURSDAY, SEPTEMBER 21 the contractor will be making a water main connection at the intersection of BROWN and ALLES. In order to complete the work the water system on Alles at Brown on Brown between Oak and Alles must be temporarily shut down. THE WATER MAIN IS SCHEDULED TO BE SHUT DOWN ON SEPTEMBER 21 BETWEEN 9AM AND 1PM.