2017 CIP - Contract B – Project Update 9/16/17

All work is weather dependent. Unknown utility conflicts may cause delays.

THE CONTRACTOR WILL BE WORKING ON SATURDAY SEPTEMBER 16. SCHEDULED WORK ITEMS INCLUDE:

Miscellaneous project cleanup on CAMPBELL

Placing stone base and framing miscellaneous sidewalks on CAMPBELL

Excavating, placing stone base and framing driveways and sidewalks on W VILLA 

CAMPBELL AVE:

The contractor will continue placing concrete sidewalks on CAMPBELL this week.

WEST VILLA DR:

The contractor will continue placing concrete driveways and sidewalks on the west side of WEST VILLA this week.

FIRST AVE:

The contractor will begin the roadway construction phase on FIRST mid to late this week. More information will be available soon.

BROWN ST:

The contractor will continue installation of the water main on BROWN.