2017 CIP - Contract B – Project Update 8/23/17

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue storm sewer installations, repairs and replacements at various locations on CAMPBELL.

The contractor will continue the roadway construction phase on CAMPBELL.

WEST VILLA DR:

The contractor will continue storm sewer installations, repairs and replacements at various locations on WEST VILLA.

The contractor will continue work on transferring existing water services to the new water main on WEST VILLA.

ON WEDNESDAY, AUGUST 23 and THURSDAY, AUGUST 24 the contractor is scheduled to complete water main connections at various locations on WEST VILLA. The scheduled water main shut downs are as follows:

EAST VILLA (Southeast to Hoffman) AUGUST 23 from 9AM to 1PM

SOUTHEAST (West Villa to West Grant) AUGUST 23 from 1PM to 3PM

WEST VILLA (Southeast to Southwest) AUGUST 24 from 8AM to 12PM

WEST VILLA (at Northwest) AUGUST 24, from 12PM to 3PM

 

FIRST AVE:

The contractor will begin construction on FIRST starting the week of AUGUST 28. More information will be available soon. Click the link below for the notification.