2017 CIP - Contract B – Project Update 8/15/17

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue storm sewer installations, repairs and replacements at various locations on CAMPBELL.

On TUESDAY, AUGUST 15 and WEDNESDAY, AUGUST 16, the intersection at CAMPBELL and WHITE will be closed to all traffic in order to install new storm sewer.

On WEDNESDAY, AUGUST 16, the contractor will begin the roadway construction phase on CAMPBELL. As part of this phase, all pavement, all curb, all driveway aprons, and sidewalks indicated in spray paint will be removed. After removing the pavement, curb and sidewalks, the contractor will excavate for the pavement base. Then a new stone base will be placed and graded. The contractor typically works in 500 to 600 foot sections at a time. Click the link below for more information.

WEST VILLA:

The contractor will continue storm sewer installations, repairs and replacements at various locations on WEST VILLA.

On TUESDAY, AUGUST 15, the contractor will begin work on transferring existing water services to the new water main on WEST VILLA.  The contractor anticipates transferring 6-8 services per day.  It will take approximately 10 days to transfer all services.  All work is weather dependent and unknown utility conflicts may cause delays.

This activity consists of turning off your water for approximately 1-2 hours and constructing the necessary piping to make the connection.  The contractor will notify you immediately prior to shutting down your service.  The contractor will be working diligently to make the connections as quickly as possible.  As soon as the work is complete, your water service will be turned back on.