2017 CIP - Contract B – Project Update 7/27/17

All work is weather dependent. Unknown utility conflicts may cause delays.

This week the contractor will continue work on transferring existing water services to the new water main on CAMPBELL between River and Cora.

On FRIDAY, JULY 28, the contractor will begin work on transferring existing water services to the new water main on Campbell between Cora and Center. The contractor anticipates transferring 6-8 services per day. It will take approximately 5 days to transfer all services. Click the link below for the resident notice.

The contractor will continue tree removals on WEST VILLA, BROWN and FIRST.

The contractor will continue water main installation on West Villa. Work will begin at West Villa and Northwest Place and proceed to the south to Southeast Place.