2017 CIP - Contract B – Project Update 7/26/17

All work is weather dependent. Unknown utility conflicts may cause delays.

This week the contractor will continue work on transferring existing water services to the new water main on CAMPBELL between River and Cora.

Testing of the newly installed water main on CAMPBELL between Cora and Center will continue. The contractor will flush the new main and test it per EPA requirements. Once approved, individual water services will be transferred to the new main. More information will be available soon.

The contractor will continue tree removals on WEST VILLA, BROWN and FIRST.

The contractor will continue project layout on WEST VILLA. Other preparatory work will also take place including material deliveries and underground utility locating.

On THURSDAY, JULY 27 the contractor will begin water main installation on West Villa starting. Work will begin at West Villa and Northwest Place and proceed to the south to Southeast Place. It is anticipated this phase work will take approximately 15 days. Click the link below for the resident notification.

W VILLA - water main installation

On THURSDAY, JULY 27 a connection to the existing water main system near the intersection of West Villa and Northwest. To perform this work a water main shut down has been scheduled for EAST VILLA DRIVE from NORTHWEST PLACE to NORTHEAST PLACE. The water main will be shut down from 9am to 1pm. Click the link below for the resident notification.

EAST VILLA water mian shut down