2017 CIP - Contract B – Project Update 7/24/17

All work is weather dependent. Unknown utility conflicts may cause delays.

This week the contractor will continue work on transferring existing water services to the new water main on CAMPBELL between River and Cora.

Testing of the newly installed water main on CAMPBELL between Cora and Center will continue. The contractor will flush the new main and test it per EPA requirements. Once approved, individual water services will be transferred to the new main. More information will be available soon.

The contractor will continue work on sanitary sewer repairs on CAMPBELL at various locations.

On MONDAY, JULY 24 the contractor will begin tree removal on WEST VILLA, BROWN and FIRST.

On TUESDAY, JULY 25 the contractor will begin project layout on WEST VILLA. Other preparatory work will also take place including material deliveries and underground utility locating. Click the link below for the resident notification.

It is anticipated the water main installation on WEST VILLA will begin later this week or early next week. More information will be available soon.