2017 CIP - Contract B – Project Update 7/19/17

All work is weather dependent. Unknown utility conflicts may cause delays.

The contractor will work on sanitary sewer repairs at various locations.

On JULY 20, the contractor will begin work on transferring existing water services to the new water main on Campbell between River and Cora. The contractor anticipates transferring 6-8 services per day. It will take approximately 15 days to transfer all services. For more information, click the link below.

Testing of the newly installed water main on Campbell between Cora and Center will continue. The contractor will flush the new main and test it per EPA requirements. Once approved, individual water services will be transferred to the new main. More information will be available soon.