News Details

2017 CIP - Contract B – Project Update 6/19/17

All work is weather dependent. Unknown utility conflicts may cause delays.

CAMPBELL AVE:

The contractor will continue tree removals.

ON TUESDAY JUNE 20, the contractor will begin construction of the new water main on Campbell Avenue. A few days of preparatory work will take place including equipment mobilization, material delivery, saw cutting pavement, and pavement removal. Pipe installation is anticipated to begin on Thursday June 22.

The contractor will begin at Campbell and River Rd and proceed to the west to Center St. It is anticipated this phase work will take approximately 20 days.

Click the link below for the resident notice.

( View PDF )