2016 Contract B - Construction Update 10/8/16

Cambridge Road (Northwest Highway to Wisconsin)

The contractor has opened up driveway access for the east side of Cambridge. They will continue to remove the west side of sidewalk and excavate for new driveway aprons on Saturday, October 8, through Tuesday, October 11.  The concrete subcontractor is scheduled to begin pouring the new sidewalk on Wednesday, October 12. The curb and driveway aprons will then be poured on Thursday and Friday, all weather permitting. One side of Cambridge is being completed at a time to prevent all residents from losing driveway access at the same time. Should all the concrete be poured according to plan, the contractor will prepare for paving on Tuesday, October 18, and pave the first layer of asphalt pavement on Wednesday, October 19.

If you have any questions related to this project, please contact Eric Heiker at (847) 561-0720 or eheiker@desplaines.org