2016 Contract A - Construction Update 10/4/16

All work is weather dependent and unknown utility conflicts may cause delays.

The contractor has completed the topsoil and sod in the parkways on WEST GRANT and NORTHWEST.

The contractor will continue to adjust b-boxes in the parkways and utility frames in the pavement to the final grade on WEST GRANT and NORTHWEST.

Miscellaneous concrete punchlist work will be done this week on WEST GRANT and NORTHWEST.

On Tuesday, October 4, the contractor will begin working on the concrete aprons on GOOD. This phase involves excavating, framing and pouring the concrete driveway aprons. Click the link below for the resident notice.

The contractor will adjust utility frames in the pavement to the final grade on GOOD.

The contractor continue installing the water main on ACRES Lane from the south end of the pavement to the south across the creek. A final connection will be made near Apple Creek Lane.

( Good Avenue - Concrete Apron Work )