2016 Contract A - Construction Update 10/3/16

All work is weather dependent and unknown utility conflicts may cause delays.

The contractor will continue to place topsoil and sod in the parkways on WEST GRANT and NORTHWEST.

The contractor will continue to adjust b-boxes in the parkways and utility frames in the pavement to the final grade on WEST GRANT and NORTHWEST.

The contractor is anticipated to excavate, frame and pour concrete driveway aprons on GOOD this week. More information will be available concerning this schedule at a later date.

The contractor will adjust utility frames in the pavement to the final grade on GOOD.

The contractor continue installing the water main on ACRES Lane from the south end of the pavement to the south across the creek. A final connection will be made near Apple Creek Lane.