2016 Contract A - Construction Update 9/24/16

All work is weather dependent and unknown utility conflicts may cause delays.

On SATURDAY, SEPTEMBER 24, the Contractor will be working on various items on WEST GRANT and NORTHWEST. We appreciate your cooperation and patience.

The contractor will continue to clean and prepare parkways for new topsoil and sod on WEST GRANT and NORTHWEST.

The contractor will continue to adjust utility frames in the pavement to the final grade on WEST GRANT and NORTHWEST.

The contractor is anticipated to excavate, frame and pour concrete driveway aprons on GOOD this week. More information will be available concerning this schedule at a later date.

On Monday, September 26, the contractor will begin transferring individual water services on ACRES.

The contractor will complete approximately 3-4 services each day. It is anticipated this phase will take approximately 3 days. Click the link below for more information.