2016 Contract A - Construction Update 9/6/16

All work is weather dependent and unknown utility conflicts may cause delays.

The concrete work will begin on the WEST SIDE OF WEST GRANT beginning Tuesday, September 6. Driveways affected will have NO ACCESS for approximately 14 days while the contractor frames and pours the curb, sidewalk and driveway aprons in these areas. Click below for the respective resident notices.

West Grant - Southwest to Southeast - Concrete WEST

West Grant - Northwest to Southwest - Concrete WEST

The contractor will begin cleaning the parkways and preparing for topsoil placement on NORTHWEST and the EAST SIDE OF WEST GRANT.

The pavement restoration work on GOOD Ave will begin within the next week. No schedule has been set for this work at this time.

The contractor will continue water main installation on ACRES Lane.