2016 Contract A - Construction Update 9/1/16

2016 Contract A - Construction Update 9/1/16

All work is weather dependent and unknown utility conflicts may cause delays.

The concrete work will continue on NORTHWEST and the EAST SIDE OF WEST GRANT.

The contractor will continue storm sewer installation on GOOD, between Suffield and Ballard.

On Thursday, September 1, the contractor will be making a connection to the existing water system at ACRES Lane, south of Miner St.  In order to complete this work, the water main on Acres will need to be shut down.  The water shut down has been scheduled for September 1, between 9am and 1pm.  Click the link below for the resident notice.

( Acres Lane - Water Main Shut Down )