2016 Contract A - Construction Update 8/15/16

All work is weather dependent and unknown utility conflicts may cause delays.

The roadway work will continue on Northwest and West Grant. This phase included the removals of existing pavement, driveway aprons and sidewalk, and excavation for and placement of new stone base. Concrete work will begin after all base is placed. No schedule has been determined at this time.

The Good Avenue water main is now the testing phase. It will take approximately one week to perform the tests. Once testing is complete an approved, the contractor will transfer water services to the new main. More information will be available at a later date.