2016 Contract A - Construction Update 7/28/16

All work is weather dependent and unknown utility conflicts may cause delays.

The contractor will continue various storm sewer installation and repairs on West Grant.

It is anticipated that the roadway work (pavement, apron, sidewalk removal and replacement) on West Grant will begin the week of 8/1.

The contractor will begin construction on Good Avenue on Thursday, July 25.  They have 1-2 days of preparatory work to complete.  It is anticipated the contractor will begin installing new water main on Monday, August 1.  It is anticipated that this work will take approximately 10 days.  Click the link below for more information.

( Good Avenue - Water Main Installation )