2016 Contract A - Construction Update 6/21/16

All work is weather dependent and unknown utility conflicts may cause delays.

The contractor will continue transferring water services to the new main on West Grant between Northwest and Hoffman.

The newly installed water main on West Grant from Hoffman to Southeast has been approved for operation. The contractor will begin transferring water services in this segment on Wednesday, June 22. It is anticipated this work will take approximately 15 days.  Click the link below for the resident notice and information.

The City has completed layout of sewer repairs and determined that several trees will need to be removed on West Grant. Trees to be removed will be marked with an “X” in pink spray paint. The contractor will remove trees within the next two weeks.