News Details

2016 Contract A - Construction Update 6/20/16

All work is weather dependent and unknown utility conflicts may cause delays.

The contractor will continue transferring water services to the new main on West Grant between Northwest and Hoffman.

The newly installed water main on West Grant from Hoffman to Southeast is currently in the testing phase. Once approved to put into service, the contractor will begin transferring water services in this segment. It is anticipated the service transfers will begin on Tuesday, June 21. More information will be available once the schedule is set.

The City has completed layout of sewer repairs and determined that several trees will need to be removed on West Grant. Trees to be removed will be marked with an “X” in pink spray paint. The contractor will remove trees within the next two weeks.