2016 Contract A - Construction Update 6/9/16

All work is weather dependent and unknown utility conflicts may cause delays.

On Thursday, June 9, the contractor will begin transferring water services on West Grant between Northwest and Hoffman. This phase of work is expected to take approximately 12 days. Click the link below for more information.

On Saturday, June 11, the contractor is tentatively scheduled to flush the new water main on West Grant from Hoffman to Southeast. This is in preparation for testing the main. There may be periods of low water pressure while the contractor is flushing the system.

On Monday, June 13, the contractor is tentatively scheduled to begin installing the new storm sewer on Northwest between West Villa and West Grant. More information will be available once the schedule is finalized.

( West Grant water service transfer (Northwest to Hoffman) )