2016 Contract A - Construction Update 5/31/16

All work is weather dependent and unknown utility conflicts may cause delays.

The contractor will continue installing the new water main on West Grant. Note that there may be intermittent closures in the intersections at Hoffman and Southwest order to complete the work.

The contractor will also complete miscellaneous sanitary and sewer repairs at various locations on West Grant.

The contractor may also begin installing new storm sewer on Northwest.

The contractor will begin testing the newly installed water main on Northwest (Villa to Grant) and West Grant (Northwest to Hoffman). Once approved, the contractor will begin transferring individual services to the new main.