2016 Contract A - Construction Update 5/17/16

The water main work on West Grant Drive will begin on Tuesday, May 17.

The contractor will begin at Northwest Place and proceed to the south to Southeast Place. It is anticipated this phase work will take approximately 25 days. 

Note that all work is weather dependent and unknown utility conflicts may cause delays.

The water main installation operation typically involves working on a small area at a time, excavating ahead of the pipe installation, installing the pipe, then backfilling the area. The contractor anticipates installing approximately 100 to 200 feet of pipe per day. You will be notified of water main shutdowns as the project progresses. Individual services will be transferred to the new main at a later date once the main has been tested and approved.