2016 Contract A - Construction Update 5/12/16

The water main work on Northwest Place will begin on Friday, May 13.

The contractor will begin with a connection at the intersection of Northwest and West Villa, and proceed to the north to West Grant. It is anticipated this phase work will take approximately 5 days. 

Note that all work is weather dependent and unknown utility conflicts may cause delays.

The water main installation operation typically involves working on a small area at a time, excavating ahead of the pipe installation, installing the pipe, then backfilling the area. The contractor anticipates installing approximately 100 to 200 feet of pipe per day. You will be notified of water main shutdowns as the project progresses. Individual services will be transferred to the new main at a later date once the main has been tested and approved.